REALIZATIONS
WE DEVELOP RES PROJECTS IN POLAND
- Podlasie 111 locations for EW with a total capacity of 799 MW.
- Podlasie energy storage with a capacity of 100 MW and EW generation sources with a capacity of 65 MW and PV with a capacity of 32 MW.
- Opole region: 14 EW locations with a total capacity of 100 MW.
- Silesian energy storage with a capacity of 300 MW and a PV generation source with a capacity of 250 MW.
- Podlasie: 12 EW locations with a total capacity of 36 MW.
- Małopolska energy storage with a capacity of 120 MW and a PV generation source with a capacity of 120 MW
- Silesian energy storage with a capacity of 100 MW and a PV generation source with a capacity of 100 MW.

Our achievements
- Energia Przykona IX Sp. z o. o. Ziębice, Ząbkowice Śląskie, Ciepłowody, Wind farm project with a total capacity of 250MW.
- Energia Przykona sp. Z o. o. Opole 294 EW project located in 8 communes with a total capacity of 945 MW with connection conditions issued through the connection of GPZ Groszowice 83MW, GPZ Rybnik 225 MW and GPZ Blachownia 180 MW.
- Neo Energia Przykona Sp. z o. o. PV Szczecinek project 506 MW.
- Neo Energia Przykona I Sp. z o. o. Ruja Wądroże with a capacity of 150 MW.
- Energia Przykona IX Sp. z o. o. Łambinowice EW project with a capacity of 60MW.
- Energia Przykona X Sp. z o. o. PV Sulmierzyce with a connection capacity of 100MW PV.
- Neo Energia Przykona II Sp. z o. o. Suwałki PV with a connection capacity of 150 MW.
- Neo Energia Przykona IV Energy storage OPOLE – GROSZOWICE 150 MW.
- Neo Energia Przykona V Energy Storage in Ząbkowice Śląskie with a connection capacity of 150 MW.
- Neo Energia Przykona VI Sp. z o. o. Energy storage facilities in Grudziądz, connection capacity 200 MW.
- Neo Energia Przykona VII Sp. z o. o. Energy Storage Kielce, connection capacity 180 MW.
- Neo Energia Przykona VIII Sp. z o. o. EW Sośno connection capacity 60 MW.
- Neo Energia Przykona IX Sp. z o. o. Kostrzyn PV connection capacity 250 MW.
- Neo Energia Przykona X Sp. z o. o. Pawłowiczki warehouse, connection capacity 220 MW.
- Neo Energia Przykona XII Sp. z o. o. Energy storage Zgierz, connection capacity 100 MW.
- Neo Energia Przykona Sp. z o. o. Kawęczyn Project EW, connection capacity 72 MW.
- Neo Energia Przykona XIV Sp. z o. o. Energy storage Zgorzelec, connection capacity 200 MW.
- Neo Energia Przykona XVI Sp. z o. o. Turów Częstochowa energy storage, connection capacity 150 MW.
POWER PLANTS UNDER CONSTRUCTION
- Energia Przykona Sp. z o. o. 600 MW, 205 MW under construction.
- Taon Sp.zoo. Kazimierz Biskupi connection capacity 150 MW.

Design „Siewierz”
INVESTMENT LOCATION
- Voivodeship: Silesia.
- District: Będzin.
- Commune: City of Siewierz.
- Precinct: Siewierz.
Project "WIND FARM gŁUBCZYCE”
INVESTMENT LOCATION
- Voivodeship: Opole Province.
- County: Głubczyce.
- Commune: Głubczyce.
- District: Pomorzowice, Klisino, Lisięcice, Zawiszyce, Debrzyca.
Basic Project Data „Głubczyce”
- The designed energy storage facility has a connection capacity of 100 MW.
- Designed power of EW is 100 MW.
- Investment area: 240.1189 ha.
- Connection point for GPZ Tauron "Głubczyce" 110kv.
WIND POWER POWER PLAN project „bielsk podlaski”„boćki”
INVESTMENT LOCATION
- Podlaskie Voivodeship.
Bielsko County.
Bielsk Podlaski commune, Boćki.
Podstawowe Dane Projektu
- Projektowany Magazyn energii moc przyłączeniowa 200MW.
- Projektowana moc: EW 799,2 MW.
- 111 EW Turbina Vestas V172-7.2 EnVentus.
- Miejsce przyłączenia: GPZ PSE Operator ”NAREW” 400/110 kv.